A building construction work can be completed by two masons A and B together in 22.522.5 days. Mason A alone can complete the construction work in 2424 days less than mason B alone. Then mason A alone will complete the construction work in :

  • A

    4242 days

  • B

    2424 days

  • C

    3636 days

  • D

    3030 days

Answer

Correct answer:C

Step-by-step solution

Standard Method

Given: Let mason AA alone take xx days and mason BB alone take yy days.

  • Together they complete the work in 22.522.5 days.
  • Mason AA takes 2424 days less than mason BB, so y=x+24y = x + 24.

Find: The number of days taken by mason AA alone.

This is a work-time problem. In one day, mason AA completes 1x\frac{1}{x} of the work and mason BB completes 1y\frac{1}{y} of the work. Together, they complete 122.5=245\frac{1}{22.5} = \frac{2}{45} of the work per day.

Using the given relation:

1x+1y=122.5=245\frac{1}{x} + \frac{1}{y} = \frac{1}{22.5} = \frac{2}{45}

with

y=x+24y = x + 24

Substitute yy into the work equation:

1x+1x+24=245\frac{1}{x} + \frac{1}{x+24} = \frac{2}{45} x+24+xx(x+24)=245\frac{x + 24 + x}{x(x+24)} = \frac{2}{45} 2x+24x2+24x=245\frac{2x + 24}{x^2 + 24x} = \frac{2}{45} 45(x+12)=x2+24x45(x + 12) = x^2 + 24x 45x+540=x2+24x45x + 540 = x^2 + 24x x221x540=0x^2 - 21x - 540 = 0

Factorizing:

x236x+15x540=0x^2 - 36x + 15x - 540 = 0 x(x36)+15(x36)=0x(x-36) + 15(x-36) = 0 (x36)(x+15)=0(x-36)(x+15) = 0

So, x=36x = 36 or x=15x = -15. Since time cannot be negative, x=36x = 36.

Therefore, mason A alone will complete the work in 3636 days. The correct option is C.

Option Check

Given: Mason AA takes xx days and mason BB takes x+24x+24 days.

Find: Which option satisfies the combined work rate 122.5=245\frac{1}{22.5} = \frac{2}{45}.

Check option C: if x=36x = 36, then y=60y = 60.

136+160=5+3180=8180=245\frac{1}{36} + \frac{1}{60} = \frac{5+3}{180} = \frac{8}{180} = \frac{2}{45}

This matches the required combined rate.

Therefore, mason A alone completes the work in 3636 days, so the correct option is C.

Common mistakes

  • Taking the relation between the times incorrectly as y=x24y = x - 24. This is wrong because mason A takes 2424 days less than mason B, so B must take more time. Use y=x+24y = x + 24 instead.

  • Using the combined time directly as 145\frac{1}{45} instead of 122.5=245\frac{1}{22.5} = \frac{2}{45}. This gives the wrong quadratic equation. First convert 22.522.5 correctly into a fraction before solving.

  • Accepting the negative root of the quadratic equation. Time taken to complete work cannot be negative, so after solving the quadratic, reject the negative value and keep only the positive feasible root.

Practice more Quadratic Equations in Complex Numbers questions

Get unlimited AI-adaptive practice, mastery tracking, and an AI tutor that explains every step — free to start.

Related questions